10. The adjacency list below is for an AOE network. The end field points to a list of adjacent vertices, durfield is the duration of the activity, link field points to another adjacent vertex, vertex field is the id ofthe adjacent vertex, count filed is the number of immediate predecessors. Which of the followingstatements are true?


(A) The total duration of the critical path is 18.
(B) Path 0, 1, 4, 6, 8 is not a critical path.
(C) Path 0, 2, 4, 7, 8 is a critical path.
(D) The latest time that event 4 (i.e., vertex 4) can occur is 8.

參考答案

答案:[無官方正解]
難度:計算中-1
書單:沒有書單,新增