60 On June 1, Todd agrees to sell and Wayne agrees to buy goods to be delivered in October at a designatedport. The port is subsequently closed by quarantine regulations during the entire month of October; nocommercially reasonable substitute performance is available, and Todd fails to deliver the goods. Todd isnot liable to Wayne for breach of contract because Todd’s performance is made___________ without his fault.
(A) unimaginable
(B) impracticable
(C) impossible
(D) inconceivable

參考答案

答案:B,C