問題詳情
40 假設有如下圖之預定進度之對應預算 BCWS(Budgeted Cost of Work Scheduled)、實際進度之對應預算 BCWP(Budgeted Cost of Work Performed)及實際進度之發生成本 ACWP(Actual Cost of Work Performed)工程績效評估管制現況,下列敘述何者正確?