40. Which item listed below would NOT be among the five specific criteria forproject selection?
(A)backing from management
(B)availability ofresources for the project
(C)high interest in a project technical featuresamong the programming staff
(D)contribution of the project towardfurthering or improving organizational goals or performance

參考答案

答案:C