41. How much time should be spent performing a feasibility study?
(A)only aslong as needed to determine feasibility in broad terms
(B)as much time asmanagement will allow since that is the only way to prevent project failure
(C)as much time as possible to save time in the later stages of projectdevelopment
(D)feasibility studies typically comprise at least half of the totaltime required for a project

參考答案

答案:A
難度:計算中-1