177.Based on Tracy's schedule, which of the following activities has the longest duration?
(A)Marketing campaign review.
(B)Vendor negotiations.
(C)Supplier evaluation.
(D)Farewell reception for Frank.

參考答案

答案:C
難度:計算中-1
書單:沒有書單,新增

用户評論

台中大雅家教-睿智數學及英】評論

Based on Tracy's schedule, which of the following activities has the longest duration?解答:本題解題重點在the longest duration 最長的期間,我會先掃每個選項的Activity第2欄位,然後逐一往回找Time第1欄位,最長的期間,以這4個選項來看,就是從13:00-14:30,1個半小時最長,當然就選C答案了。(A) Marketing campaign review. 08:30-09:30(1小時) (X)